USP&E on October 17th, 2014
USP&E on October 17th, 2014
USP&E on October 17th, 2014
USP&E on January 24th, 2012

USP&E is pleased to announce that we have completed construction of our newest Containerized HFO Power Plant in Marampa, Sierra Leone, Africa. This 12.9 MW power plant is now fully operational and powering a productive iron mine in Sierra Leone.

The entire USP&E Global team worked together to successfully complete the power plant on time and on budget to the client’s satisfaction.  Our team of experienced engineers and technicians achieved exceptional results. As a result, USP&E was awarded a five-year operations and maintenance contract.

“We are thrilled with our results, but even more so with the overall success of our partnership with our client. It took everything we had and more to get this done and are very grateful for the work,” said Jason Biermeier, COO/Executive VP of USP&E.

Lights from First Electricity Generated by HFO Power Station in Sierra Leone

Tags: ,

USP&E on August 2nd, 2011

Tags:

USP&E on August 1st, 2011

Tags:

USP&E on July 29th, 2011

Tags: ,

USP&E on July 22nd, 2011

USP&E on July 21st, 2011
USP&E on July 20th, 2011
USP&E on July 18th, 2011
USP&E on July 16th, 2011
USP&E on July 12th, 2011
USP&E on July 8th, 2011
USP&E on June 13th, 2011

Generators 7 and 8 arrive on site, bringing total capacity to 12.8 MW!

USP&E on June 2nd, 2011

With generators 5 and 6, power generation capacity reaches 9.6 MW.

USP&E on May 17th, 2011

We’re on a roll now. HFO Generators 3 and 4 have arrived on-site, bringing the total electricity generation capacity to 6.4 MW. Supporting equipment is starting to arrive as well. The HFO Purifying container was also placed onto its pad yesterday.

USP&E on May 16th, 2011

The first 2 containers that arrived in port now have made it to the construction site and are being placed on their concrete foundations. Since these are 1.6 MW HFO Generators, by the end of the day 3.2 MW of electricity generating potential is in place and waiting.

USP&E on May 14th, 2011

The first two of our many (92) containers have arrived in port in Freetown, Sierra Leone, Africa. Now, they just have to be loaded onto trucks so they can make the 2 hour journey to the construction site.

USP&E on May 13th, 2011

Dirt and foundation work continues in Sierra Leone. The great thing about our containerized generators and equipment is that there is no further construction required. Once these concrete and steel bases are ready then our equipment goes on top. Container-by-container a complete power plant quickly emerges.