USP&E on April 3rd, 2020

USP&E NOW HAS 5 unique power station assets as follows:

20MW NEW SURPLUS WARTSILA 50HZ PLANT WITH BOP

17.5MW Natural Gas Power Plant ZERO Hour.
Uninstalled. 2 x Wartsila 20V34 SG Generator Sets

32MW NEW SURPLUS MAN HFO 50HZ PLANT WITH BOP

GAS TURBINE PACKAGE- SOLAR TAURUS 60

82MW NEW NATURAL GAS ROLLS ROYCE + SIEMENS Combined Cycle Gas Turbine Power Station

2 x 10.2MW HFO/Diesel Wartsila 20V32TS • Generating Sets • $8m

See USP&E 20MW Wartsila DATASHEET

USP&E Global is offering the sale of two (2) Wärtsilä 20V32TS engines and related equipment (the “Gensets”).

The Gensets were purchased as components of a 60MW power plant. The attached Extract of Technical Data for certain equipment provides engineering specifications relevant to the listed items.
This package is available at both 10.2MW and 20MW.

• 17.5MW Natural Gas Power Plant ZERO Hour • Uninstalled. 2 x Wartsila 20V34 SG Generator Sets• $5.9m

See USP&E 17MW 20V34-SG Wartsila Natural Gas Gensets DATASHEET

Made in 2009 and NEVER installed. All equipment is intact and is complete with installation & operation manuals, other documentation, and spare parts! The generators have the original preservation from the factory, as they are never installed. These units have been inspected and the machines were found in flawless condition upon inspection. This complete power plant equipment including building structures is still in original shipment crates.

32MW HFO MAN 18V3240 • NEW SURPLUS POWER PLANT • $14.5m

EXCLUSIVE FROM USP&E!

See USP&E 32MW MAN 18V3240 Power Plant DATASHEET

USP&E Global hereby presents a 32MW New Surplus HFO Power Plant. The equipment includes Generating Sets (4 x MAN generating sets) and Fuel treatment Modules (4 x 40’ containers of fuel treatment, pumping and booster modules). All the other imported equipment is in a warehouse in a clean and dry environment.

Gas Turbine Package- Solar Taurus 60 $340k

USP&E Solar Taurus 60 Gas Turbine Package DATASHEET

USP&E Global hereby presents Solar Taurus 60 Gas Turbine Package.
The equipment is being stored in accordance with instructions provided by the OEM

NEW 82MW ISO Natural Gas Combined Cycle Power Plant
Rolls Royce Trent 60 (SGT-A65) Gas Turbine & Siemens SST-300 STG $24m

See USP&E 82MW Unused Natural Gas Power Plant DATASHEET

USP&E Global hereby presents an unused 82MW ISO rated combined cycle power plant. The plant’s main equipment is composed of a Trent 60 DLE Gas Turbine (also known as the SGT-A65), a Nooter/Eriksen HRSG, and a Siemens SST-300 Steam Turbine. The plant equipment was manufactured between 2016 and 2018 and was mainly delivered to the site in 2018. Plant installation started in May 2017 and was stopped in February 2018 due to a lack of gas supply and cancellation of Government project incentives. The plant has been under preservation since construction was stopped in February 2018.

USP&E on October 17th, 2014

USP&E HOTLIST 2019

Email Us Today for these GREAT DEALS! Guaranteed response within 2 hours!!

USP&E on October 17th, 2014

USP&E on October 17th, 2014

USP&E on January 24th, 2012

USP&E is pleased to announce that we have completed construction of our newest Containerized HFO Power Plant in Marampa, Sierra Leone, Africa. This 12.9 MW power plant is now fully operational and powering a productive iron mine in Sierra Leone.

The entire USP&E Global team worked together to successfully complete the power plant on time and on budget to the client’s satisfaction.  Our team of experienced engineers and technicians achieved exceptional results. As a result, USP&E was awarded a five-year operations and maintenance contract.

“We are thrilled with our results, but even more so with the overall success of our partnership with our client. It took everything we had and more to get this done and are very grateful for the work,” said Jason Biermeier, COO/Executive VP of USP&E.

Lights from First Electricity Generated by HFO Power Station in Sierra Leone

Tags: ,

USP&E on August 2nd, 2011

Tags:

USP&E on August 1st, 2011

Tags:

USP&E on July 29th, 2011

Tags: ,

USP&E on July 22nd, 2011

USP&E on July 21st, 2011

USP&E on July 20th, 2011

USP&E on July 18th, 2011

USP&E on July 16th, 2011

USP&E on July 12th, 2011

USP&E on July 8th, 2011

USP&E on June 13th, 2011

Generators 7 and 8 arrive on site, bringing total capacity to 12.8 MW!

USP&E on June 2nd, 2011

With generators 5 and 6, power generation capacity reaches 9.6 MW.

USP&E on May 17th, 2011

We’re on a roll now. HFO Generators 3 and 4 have arrived on-site, bringing the total electricity generation capacity to 6.4 MW. Supporting equipment is starting to arrive as well. The HFO Purifying container was also placed onto its pad yesterday.

USP&E on May 16th, 2011

The first 2 containers that arrived in port now have made it to the construction site and are being placed on their concrete foundations. Since these are 1.6 MW HFO Generators, by the end of the day 3.2 MW of electricity generating potential is in place and waiting.

USP&E on May 14th, 2011

The first two of our many (92) containers have arrived in port in Freetown, Sierra Leone, Africa. Now, they just have to be loaded onto trucks so they can make the 2 hour journey to the construction site.